Deegan Backs More Downtown Investment After Amendment 3. What’s in the Pipeline and What’s Coming Due?

John Hawley

Nov 16, 2026

The Development Divide: Part 28

Mayor Donna Deegan is making the case for Jacksonville to double down on downtown development incentives after Amendment 3. In a November 10 interview with Anne Schindler on WJCT’s First Coast Connect, she called Gateway Jax’s Publix-anchored project “a really smart investment” and argued that the property-tax cut makes commercial development especially important. Her position is that expanding the commercial tax base can help make up for some of the revenue Jacksonville will lose as homestead exemptions grow.

Council approved the $28.25 million cash grant for the Publix tower that night. It also received a new Gateway request for $20 million in cash for a hotel and residential tower at Riverfront Plaza, a proposal the Downtown Investment Authority had already endorsed. The DIA has also recommended an $8 million cash grant for a Southbank Marriott and is reviewing a Hard Rock Hotel proposal. Meanwhile, two reporting deadlines appear to have passed for the proposed Culinary Institute of America campus and hotel, and neither progress report turned up in the public records reviewed.

The Council Auditor’s estimates reported around the November vote put Jacksonville’s property-tax revenue loss at about $200 million in fiscal 2027–28 and $300 million in fiscal 2028–29. September coverage had put the first-year loss at $180 million. As Council prepares those budgets, the decisions ahead include when existing commitments come due, which public accounts will cover them and what Jacksonville should require before it approves new grants, including whether to reserve a share of the housing for local workers.

The Culinary Institute deal has passed its first two reporting milestones

On April 15, the DIA board authorized exclusive talks with Corner Lot and Aspect Real Estate Group for the city-owned site at 330 E. Bay St. The proposed Culinary Institute campus would anchor a hotel and conference center. In May, Council authorized negotiations for up to $35 million in campus-related incentives. Preliminary terms identified $27 million from a downtown riverfront incentive fund and $8 million for workforce development. A final agreement would still need Council approval and an appropriation.

DIA Resolution 2026-04-07 starts the clock when the board chair signs it. Using the April 15 vote as the working start date, the CEO owed progress reports to the DIA board on July 14 and October 12 if a resolution to adopt a term sheet had yet to come forward. October 12 also marks the end of the initial 180-day negotiating period on that timetable. The resolution allows up to 180 additional days and calls for reports every 60 days during an extension. The first would fall around December 11 if an extension began at the end of the initial period.

DIA CEO Colin Tarbert said in September that he expected to bring a term sheet to the board in October. I could verify the board vote authorizing talks, but couldn’t independently verify the chair’s signature date or locate the two reports, an extension or a board-approved term sheet in the public materials reviewed. The resolution directs the CEO to report to the board. It does not set an online filing deadline. The record request is straightforward: the dated signature page, copies of the reports and when the CEO delivered them, any extension and the current term sheet.

The big requests still in play

Project

Cash or other public funding under discussion

Last documented step and what to watch

Gateway Jax — Riverfront Plaza

$20 million cash plus up to $35.397 million in property-tax rebates

The DIA endorsed the term sheet September 16. Council introduced 2026-0921 November 10 and assigned it to Rules, Neighborhoods and Finance. A November 24 hearing is listed. The DIA plans to use the Northbank redevelopment trust fund for the cash grant, with a later appropriation and payment upon completion under the filed proposal.

Culinary Institute / Corner Lot and Aspect

Up to $35 million in campus-related incentives under negotiation

Council authorized talks. The DIA’s reporting dates appear to have passed. The final terms should show who receives each payment, which expenses qualify and what happens if the institute or hotel changes its plans.

Hard Rock Hotel — Project Revival

$37.5 million to $75 million in possible completion grants

The DIA’s February range came from two developer models. It lists the hotel, residences and entertainment project at 500 E. Bay St. as in review. I found no published incentive term sheet, Council bill or project-specific reporting deadline.

Baptist Health — Southbank Marriott

$8 million cash plus about $12.9 million in tax rebates

The DIA approved the rebate and recommended the cash grant in January. The proposal called for two $4 million payments, anticipated at the time in 2029 and 2030. I found no final Council approval of the cash grant.

Riverfront Plaza and Baptist together represent $28 million in specifically sized cash grants that the DIA has recommended. Adding Hard Rock’s early scenarios would take those three projects to $65.5 million to $103 million, at very different stages and with different possible payment years. Keep the culinary institute’s $35 million alongside that figure as a broader incentive proposal until the final terms establish the payment structure.

The DIA’s February list also put up to $19 million against the former JEA headquarters, up to $15 million against the Laura Street Trio and $20.27 million against Independent Life. Those figures belong on a watchlist. The Trio has a new owner, and the DIA said in February it had yet to underwrite the Independent Life request. Gateway’s Ambassador Hotel had a $10 million cash request on that list, but the later DIA board action was for a $15 million repayable preservation loan. I would exclude the old cash figure from today’s tally. I found no documented reporting deadline comparable to the culinary institute’s for these projects.

What Council has already approved or set aside

Decision

Amount

What the money represents

First four Gateway Pearl Square projects, 2024

$38.95 million in completion grants

Council also approved $59.63 million in tax rebates. The cash figure predates the later transfer of $7 million from one of the projects to N7.

Future-obligations contingency, August 25

$33.958 million

Council transferred General Fund balance into a multiyear contingency for previously unfunded obligations, including completion grants and forgivable loans. This is money set aside to cover obligations already in the pipeline.

Gateway N4, N5 and N11, October 13

$9.223 million

Council appropriated cash for FY 2026–27 from previously designated contingency accounts. N4 received about $3.522 million, N5 $1.062 million and N11 $4.639 million. These are installments on the earlier Pearl Square grants.

Gateway N7 / Publix, November 10

$28.25 million cash plus up to $21.412 million in rebates

The cash plan uses $9.25 million from the city’s general budget, $12 million from DIA-controlled funds and $7 million redirected from an earlier Pearl Square grant. The $12 million includes $4 million each redirected from Shipyards West Park and the Riverfront Plaza restaurant. The full cash commitment stayed in the deal, but $7 million had already been authorized for Gateway.

These rows overlap. The October Gateway appropriation pays installments on the 2024 award, and the November Publix deal moves a piece of that earlier award. Likewise, the October 2 Council Auditor schedule showed $130.557 million in listed payments, $33.958 million designated and $96.599 million still requiring funding under the schedule’s assumptions. It included the then-pending Publix grant, UF campus payments, loans and other assistance. It gives a dated measure of the city’s broader commitments. A post-November reconciliation would show how the amended Publix funding and the October appropriations changed the remaining balance.

Which payments could hit in 2027?

Jacksonville is already in FY 2026–27, which runs through September 30, 2027. In March, the DIA identified about $44.61 million in completion grants expected to come due that fiscal year. The list included four Gateway Pearl Square projects, the Four Seasons and Shipyards development, the Juliette Balcony restoration, Corner Lot’s 520 N. Hogan St. redevelopment and the Home2 Suites project at 600 Park St. That was a forecast before later appropriations and the N7 funding change. Each actual payout depends on the project meeting its contract conditions.

Two large pieces have identifiable funding. Council funded roughly $25.835 million for the Four Seasons and Shipyards grant through $25.142 million from the city’s self-insurance fund and $693,036 from the General Fund’s budget stabilization contingency. Council also appropriated $9.223 million for Gateway N4, N5 and N11 for the current fiscal year. Together those actions identify about $35.06 million in funding for projects on the March watchlist. The figure measures appropriations. Payment dates and draws require a current disbursement ledger.

The next budget, FY 2027–28, starts October 1, 2027. That is the first budget year affected by Amendment 3. I found no updated project-by-project cash schedule showing how much will come due in that budget year or exactly how much will draw on the General Fund. The N7 agreement ties payment to later construction milestones. Riverfront Plaza would pay upon completion if Council approves it, and the early Baptist schedule pointed to later years.

The comparison with Amendment 3

Fiscal year

Expected property-tax revenue loss

FY 2027–28

$180 million in September budget coverage and about $200 million in Council Auditor estimates reported around the November vote

FY 2028–29

About $300 million in Council Auditor estimates

For scale, the $33.958 million August set-aside equals about 17% to 19% of the first-year revenue loss. The $44.61 million March estimate for FY 2026–27 grant payouts equals about 22% to 25% of that loss. Those comparisons put the amounts in perspective. The set-aside and expected payouts cover one-time obligations, while Amendment 3 reduces annual revenue. Some incentives also draw on redevelopment funds dedicated to downtown uses, so their direct competition is with other eligible projects within those districts.

When Jacksonville could see a return

Jacksonville could owe the completion grant once Gateway meets its project and grocery-store milestones, while the tax benefit would build over years and a portion of the new property-tax revenue would go back to the developer through rebates. To judge the mayor’s investment case, Council needs to see how much tax revenue Jacksonville would actually retain after the grant and rebates, when it would receive that revenue and how the estimate changes if development runs late or property values grow more slowly than expected.

What other Florida cities require for housing

The published terms reviewed for Gateway’s $28.25 million N7 cash grant and the DIA’s term sheet for the proposed $20 million Riverfront Plaza cash grant identify no set-aside for workforce or affordable housing. N7 calls for about 259 apartments and a grocery store. Riverfront Plaza would allow 50 to 150 residential units, including condos or rentals, alongside the hotel. The two cash grants total $48.25 million if Council approves Riverfront Plaza as filed.

Our Florida Cities Head-to-Head comparison found examples of Florida cities tying public funding or development rights to measurable housing commitments.

City

What the city offered

Housing commitment

Tampa

$4 million from its downtown Community Redevelopment Agency

22 of 104 apartments at 801 East Whiting became workforce housing for 50 years.

Orlando

Rezonings allowing more housing at Lake Nona and RoseArts

10% of the units authorized through those rezonings are to be affordable, for 1,288 units across the two approvals.

Miami

Miami 21 zoning incentives for qualifying affordable or workforce housing

Participating projects must record a covenant that runs with the land for at least 30 years.

Fort Lauderdale

Density bonuses under a city affordable-housing program

A 10% set-aside under the program, with a 30-year deed restriction.

Tampa offers the closest comparison to Jacksonville’s use of public cash. Orlando, Miami and Fort Lauderdale show how cities can also negotiate lasting housing commitments when they grant additional development rights.

What Jacksonville would keep if the building sells in year 10

The DIA’s financial model for Gateway’s N7 tower assumed a potential sale in year 10. If interest rates rise in response to persistent inflation, buyers could face higher borrowing costs and refinancing could leave owners with less cash to distribute to investors. Slower leasing or weaker market-rate rents would add pressure. Apartments priced within reach of more local workers could help stabilize occupancy in a softer market. Rent limits can also reduce potential income and the price a buyer is willing to pay. The mix of units, rent levels, operating costs and loan terms determines how those effects balance out.

A recorded affordability covenant could give a buyer a clear set of obligations at resale and preserve the housing benefit for Jacksonville after the original investors exit. Future deals could specify the share of units reserved, who qualifies, maximum rents or sales prices, how long the restrictions last and how the DIA will verify compliance after a transfer. Council could ask the DIA to model whether a project with those terms could still cover its debt, support investor distributions and sell in year 10 under higher borrowing costs and slower rent growth. Jacksonville would then have a way to weigh the mayor’s projected tax return alongside a housing benefit that residents could still use after the sale.

What Council and the DIA can put on the record

Council’s next budget needs an updated schedule showing each approved obligation, its expected payment year, the conditions that trigger it, its funding account and any amount still unappropriated. The DIA can answer a separate question now by producing its 330 E. Bay St. progress reports and any extension. Those two records would show which deals are advancing, which checks are coming due and how much room Council has left as property-tax revenue falls and they prepare to cut into public services to balance the budget.